Case 2 read the emirates ID case and answer the following:
Case 2 read the emirates ID case and answer the following:
- Identify potential risks that may face Emirates ID projects
- On a scale from 1-5 calculate the likelihood (probability) of each risk
- On a scale from 1-5 calculate the potential impact of each risk
- Multiply the likelihood (probability) by the potential impact to get risk score for each risk
- Classify the risks based on their scores into three groups:
1- Red (risks that have score more than 15),
2- Yellow (scores between 6 and less than 15)
3- Green (risks that less than 6)
- Illustrate the risks using a matrix like the following example: