Calculating a Time Duration Estimate
Description
You have explored several duration estimation techniques. Using the project you chose in Unit 2, complete an estimate using the expected value technique for two activities on your WBS. Provide the math as part of your answer using the expected value formula: Expected value: (optimistic + pessimistic + (4 X most likely)) / 6. Explain your reasoning for your optimistic, pessimistic, and most likely values.